8. Leases for the Fakenham Leisure and Sports Hub Project
PDF 384 KB
|
Executive Summary |
This report seeks Cabinet approval to grant a lease to UK Power Networks (UKPN) for a small area of land at Trap Lane leased from Fakenham Town Council. The lease is required for the construction and operation of a power substation to support the expanded leisure centre being constructed in the FLASH project. Construction of the substation is scheduled to commence in April 2026. There are no alternative options if the leisure centre project is to proceed.
|
|
Options considered
|
1. Approve the lease to UKPN for the substation site.
|
|
Consultation(s) |
Steve Hems - Director for Communities (Project Sponsor) Nicola Swan - Solicitor, Eastlaw
|
|
Recommendations
|
It is recommended to Cabinet to provide approval to:
· To grant a ‘99years less one day’ lease to UKPN for the construction and operation of a substation on Trap Lane land.
· Delegate approval to the Asset Strategy Manger or the Assistant Director for Finance and Assets to agree the exact terms of the above legal agreement.
|
|
Reasons for recommendations
|
The substation is essential for the leisure centre expansion project. Without this lease, the new substation cannot be built which would mean the power demands of the new facility could not be met.
|
|
Background papers
|
Report to Full Council – 27th July 2022 Report to Full Council – 20th December 2023 Report to Cabinet – 8th July 2024
|
|
Wards affected |
Fakenham wards (Lancaster North and South); and wards in the west of the district including Briston, Priory, Stibbard, Stody, The Raynhams, Walsingham; Wells with Holkham. |
|
Cabinet member(s) |
Cllr, L Shires |
|
Contact Officer |
Milo Creasey – Estates Surveyor - milo.creasey@north-norfolk.gov.uk
Renata Garfoot - Asset Strategy Manger -Renata.Garfoot@north-norfolk.gov.uk
|
|
Links to key documents:
|
|
|
Corporate Plan: |
The 2023-2027 Corporate Plan themes - Developing. our Communities and A Strong, Responsible and Accountable Council |
|
Medium Term Financial Strategy (MTFS) |
The contents of this report do not directly impact upon the MTFS. Wider financial implications of the Fakenham Leisure and Sports Hub have been considered in earlier reports to Full Council. |
|
Council Policies & Strategies |
Asset Management Plan 2018 - 2022 |
Decision:
Decision
RESOLVED to
· Grant a ’99 years less one day’ lease to UKPN for the construction and operation of a substation on Trap Lane land.
· Delegate approval to the Asset Strategy Manger or the Assistant Director for Finance and Assets to agree the exact terms of the above legal agreement.
Reason for the decision:
The substation is essential for the leisure centre expansion project. Without this lease, the new substation cannot be built which would mean the power demands of the new facility could not be met.