11. Refurbishment of the Pavilion Theatre, Cromer Pier
PDF 183 KB
|
Executive Summary |
The Pavilion Theatre auditorium has not been refurbished alongside the front and back of house. This project will improve the energy efficiency, patron comfort and provide superior facilities to ensure viability into the future unitary council control. |
|
Options considered
|
Option 1 The recommended option includes insulting the roof, walls and floor of the auditorium, providing heating and cooling and completing the front of house upgrades that were previously descoped.
Option 2 The front of house works could be excluded, but this would make less commercial sense when the theatre will be closed for the auditorium works. Not recommended
Option 3 Thirdly, no changes made to the auditorium. This would reduce thermal and noise efficiency in the winter and reduce audiences in the height of summer. Commercial opportunities might not be maximised. Not recommended
|
|
Consultation(s) |
Local ward member, Cllr Tim Adams - Leader and Cllr Lucy Shires - Portfolio Holder for Finance, Estates & Property Services
|
|
Recommendations
|
Recommendation 1 Cabinet are recommended to recommend that Full Council increase of the capital program by £2.400m funded by borrowing. Recommendation 2 That delegated authority is granted to the Assets and Property Programme Manager, in consultation with the Portfolio Holder for Finance, Estates and Property Services and the s151 Officer, to award a contract for the delivery of the works up to the approved budget. |
|
Reasons for recommendations
|
To ensure the viability and efficiency of the Pavilion Theatre, Cromer Pier for the benefit of residents and the tourism economy.
|
|
Background papers
|
Exempt appendix A cost estimate |
|
Wards affected |
All |
|
Cabinet member(s) |
Cllr Lucy Shires |
|
Contact Officer |
Dan King, Assistant Director Finance & Assets Daniel.King@North-Norfolk.gov.uk |
Decision:
Decision
RESOLVED
1. to recommend that Full Council increaseS of the capital program by £2.400m funded by borrowing.
2. That delegated authority is granted to the Assets and Property Programme Manager, in consultation with the Portfolio Holder for Finance, Estates and Property Services and the s151 Officer, to award a contract for the delivery of the works up to the approved budget.
Reason for the decision:
To ensure the viability and efficiency of the Pavilion Theatre, Cromer Pier for the benefit of residents and the tourism economy.